Hindustan Foods Q2 FY27 consolidated total income rose 18% to Rs 1,269 crore from Rs 1,076 crore a year earlier, with adjusted PAT up 22% to Rs 46 crore, EquityBulls reported on 5 November 2026. The company now expects to close FY27 at around Rs 200 crore PAT, the lower end of its Rs 200-220 crore guidance.
What Were Hindustan Foods’ Q2 FY27 Numbers?
EBITDA rose 26% to Rs 115 crore from Rs 92 crore, and PBT rose 25% to Rs 61 crore from Rs 49 crore. Adjusted PAT was Rs 46 crore against Rs 38 crore. PAT excludes a one-time loss of Rs 1.3 crore from a flood-related insurance deductible at the Silvassa facility.
Why Is Full-Year Profit Guidance at the Lower End?
The company reiterated FY27 PAT guidance of Rs 200-220 crore but now expects to close at around Rs 200 crore, with Q4 FY27 the major contributor. It attributed the shortfall to the Silvassa disruption and project commissioning delays. Group CFO Mayank Samdani said, “we reiterate our PAT guidance of Rs. 200-220 crore.”
Which Projects Are Delayed?
The Liquid Detergent plant at Silvassa is expected to normalise by the end of Q3 FY27. The Lucknow, Goa and Baddi projects are 1-2 months behind schedule and are expected to commercialise in early Q4 FY27. The footwear division’s order book provides visibility until March 2027.
Market Reaction and Industry Response
No share-price reaction or analyst commentary was found in the source reviewed.
What Happens Next?
Management expects significantly stronger cash flows in H2 FY27, after H1 FY27 operating cash flow of Rs 58 crore, and further profitability gains in the footwear division in H2.
Frequently Asked Questions
What was Hindustan Foods’ total income in Q2 FY27?
Consolidated total income was Rs 1,269 crore, up 18% from Rs 1,076 crore.
What is Hindustan Foods’ FY27 PAT guidance?
The company reiterated Rs 200-220 crore but now expects to close at around Rs 200 crore.
What caused the delay in Hindustan Foods’ projects?
The company cited the Silvassa disruption and commissioning delays; the Lucknow, Goa and Baddi projects are 1-2 months behind schedule.
Source: EquityBulls, 5 November 2026.