Indian Railways has ordered Rs 839 crore (about $94 million) of onboard systems from US-based Wabtec for the 24-coach Vande Bharat sleeper trains being developed at the Integral Coach Factory (ICF) in Chennai. The order, reported on 27 October 2026, covers brake systems, doors and gangways, plus integration, testing, commissioning and long-term support.
ICF aimed to finalise the 24-coach design by 10 November 2026, more than four years after it issued the technical specifications. A prototype is expected around May or June 2027. ICF is set to build 50 rakes of this longer version. Propulsion systems were ordered in December 2024, with Medha supplying 33 rakes and Alstom 17.
Sleeper trains in the pipeline
The 24-coach train would add eight coaches to the current 16-coach sleeper and include a dedicated pantry car. The present 16-coach train carries 823 passengers in 11 AC three-tier coaches, four AC two-tier coaches and one first-class AC coach.
Across all builders, about 260 Vande Bharat sleeper trainsets are on order:
- Kinet Railway Solutions, an Indo-Russian venture led by Rail Vikas Nigam and Transmashholding, is to build 120 16-coach sets at its Marathwada Rail Coach Factory in Latur, with a first prototype targeted by 31 March 2027.
- A BHEL–Titagarh consortium is to build 80 16-coach sets, with a first train targeted in the second half of FY27 and a 35-year maintenance contract.
- ICF will build 50 24-coach sets.
- BEML is building 10 16-coach sets. One pair started service on the Howrah–Kamakhya route in January 2026, two more pairs are ready for Delhi–Varanasi and Mumbai–Bengaluru, and two remain in production.
Some makers have pushed back deadlines in the past because of technical issues. Railways currently runs 162 Vande Bharat services, with occupancy of 98% to more than 100% on various routes.
Powder coating for rail parts
Supplier capacity is building around the rail programme. On 5 November, Jindal Lifestyle, a subsidiary of Jindal Stainless, commissioned a 5,000-tonne-a-year powder-coating facility at its Pathredi plant in Gurugram. The line uses an automated conveyor, nine water tanks, nano-based pre-treatment chemicals and modern spray equipment.
The new line will serve metro rail systems, automotive parts, medical equipment racks and luggage handling systems. The company already makes handrails, rail car body shell parts such as side walls, roofs, end walls and underframes, electrical cabinets and battery boxes. It exports to Germany, New Zealand, the UAE and Brazil.
Chief executive Dhirendra Bahadur Singh said the facility “adds an important dimension to our manufacturing capabilities.”
What it means for coatings
Each new trainset needs large amounts of coating, from exterior livery systems on stainless steel and aluminium car bodies to underframe protection, interior panels and powder-coated fittings. Rail coatings must meet strict fire, smoke and durability standards, which favours suppliers with approved, tested systems.
With roughly 260 sleeper trainsets on order, plus metro and regional rail programmes, coach builders and their component suppliers will need more coating capacity over the next three to four years. Lines such as Jindal Lifestyle’s show that some of this finishing work is moving down the supply chain, as component makers deliver fully coated parts rather than bare metal.
The repeated delays are the main risk for suppliers. Coatings demand only starts when production ramps up, and the 24-coach train is still more than six months from a prototype. The BEML sets already in service and the Kinet and BHEL–Titagarh rollouts due over the next year will give clearer evidence of production pace.
This article appeared in the November 2026 print edition of Industrial Front (Volume 7, Issue 8).